Update March 14, 1pm
2/3
240V in SBG1 is ready to be tested. Tomorrow 20KV for SBG1 will be UP.
The 20KV is SBG3 is in progress. 2 days.
Watercooling SBG1/3/4 checked and protected.
Cleaning and drying are in progress.

— Octave Klaba (@olesovhcom) March 14, 2021